BİRMEK A.Ş. has commenced installation work on the KİPAŞ KAHRAMANMARAŞ THERMAL POWER PLANT project.
Project: MAREN Kahramanmaraş 55 MW Thermal Power Plant Project
Client: MAREN MARAŞ ELEKTRİK ÜRETİM SANAYİ VE TİC. A.Ş.
Scope of Work: Installation of all mechanical equipment and piping works for the thermal power plant
1-Boiler and Auxiliary Unit installation works
2-ESP & Bag House Filter installation works
3-General piping works
4-Steam turbine and equipment installation works
Project Location: Kahramanmaraş /TURKEY
Start Date: 1 December 2022